CONSTITUENCY BRIEFING · ENERGYMAP.APP

Frome and East Somerset

MP: Anna Sabine (Liberal Democrat) England Data to July 2026

Frome and East Somerset has 87 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 32,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 38,645 homes. A 60 MW battery was refused planning here in 2026; while discharging it could have supplied about 210,000 homes.

Ranks 74 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
St Georges Cross Farm, Berkley Lane - Battery Energy StorageIntegrum SPV 23101 Limited Battery 60 MW Refused by Somerset Council in 2026Who can move it: Somerset Council · planning ref 2025/0690/FUL
Bluebell Wood Solar Farm & Battery StorageLow Carbon UK Solar Investment Co Limited Battery 50 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/2183/FUL
Bluebell Wood Solar Farm & Battery StorageLow Carbon UK Solar Investment Co Limited Solar 50 MW18,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/2183/FUL
Frome Power, Styles Close - Energy Storage FacilityTrina Solar UK Hold Co Limited Battery 30 MW Waiting 3.1 years for a planning decisionWho can move it: Somerset Council · planning ref 2023/1070/FUL
Marksbury Plain - Solar ParkRenewable Connections Developments Limited Solar 15 MW5,400 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/04881/FUL
Lodge Hill, Berkley - Solar ParkWessex Solar Energy Limited Solar 14 MW5,300 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2021/2191/FUL
Ash Farm, Charlton Road - Battery Storage SystemAsh Farm Solar Limited Battery 10 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2024/0795/FUL
Parcel 2882, Water Lane - Solar FarmPathfinder Clean Energy UK Dev Limited Solar 9.2 MW3,300 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/03894/FUL
Midsomer Norton - Battery Energy Storage SystemConrad Energy (Developments) II Limited Battery 6 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 21/03281/FUL
Lodge Farm Solar FarmEcotricity Solar 5 MW1,800 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 2011/0765
Ash Farm, Charlton Road - Solar PanelsAsh Farm Solar Limited Solar 5 MW1,800 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2024/0795/FUL

Plus 7 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Frome and East Somerset 87 MW34 MWnot visible
South West Wiltshire 74 MW71 MWnot visible
Melksham and Devizes 51 MW133 MWnot visible
Wells and Mendip Hills 78 MW131 MWnot visible
Glastonbury and Somerton 21 MW95 MWnot visible
North East Somerset and Hanham 0.5 MW5.2 MWnot visible

Frome and East Somerset has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.