CONSTITUENCY BRIEFING · ENERGYMAP.APP

North East Somerset and Hanham

MP: Dan Norris (Independent) England Data to July 2026

North East Somerset and Hanham has 5 MW of renewables running, enough for 1,900 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,439 homes.

Ranks 483 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Stowey Road, Stowey - Solar FarmRegener8 Power Solar 50 MW18,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/04156/EFUL
Gypsy Lane, Burnett - Solar PV ArraysConrad Energy (Developments) Limited Solar 24 MW8,900 homes Refused by Bath and North East Somerset Council in 2025Who can move it: Bath and North East Somerset Council · planning ref 24/02489/EFUL
East Dundry Lane, Norton Hawkfield - Solar PanelsEnviromena Solar 15 MW5,400 homes Waiting 13 months for a planning decisionWho can move it: Bath and North East Somerset Council · planning ref 25/02595/FUL
Queen Charlton Quarry Renewable Energy Facility - food wasteRSM (formerly Resourceful Earth) Anaerobic Digestion 2.2 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 13/04126/MINW
Resourceful Earth Limited - Anaerobic Digester FacilityResourceful Earth Limited Anaerobic Digestion 2.2 MW Refused by Bath and North East Somerset Council in 2022Who can move it: Bath and North East Somerset Council · planning ref 21/00419/EFUL
Fairy Hill, Compton Dando - Solar FarmEnvironmental Gain Limited / Bath & West Community Energy Limited Solar 2.1 MW800 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/04529/FUL

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
North East Somerset and Hanham 0.5 MW5.2 MWnot visible
Wells and Mendip Hills 78 MW131 MWnot visible
Frome and East Somerset 87 MW34 MWnot visible
Bath 0 MW0 MWnot visible
North Somerset 16 MW0 MWnot visible
Bristol South 1.7 MW0.2 MWnot visible

Frome and East Somerset next door has 87 MW waiting, more than North East Somerset and Hanham's 0.5 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.