Birmingham Selly Oak has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,369 homes.

Ranks 569 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Fordhouse Lane - Battery Energy Storage SystemFPC (Electric Land) Limited Battery 20 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/00142/PA

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Birmingham Selly Oak 0 MW0 MWnot visible
Bromsgrove 51 MW0.7 MWnot visible
Solihull West and Shirley 1.8 MW0 MWnot visible
Birmingham Northfield 0.9 MW0 MWnot visible
Birmingham Hall Green and Moseley 2.1 MW0 MWnot visible
Birmingham Edgbaston 0.8 MW0 MWnot visible

Bromsgrove next door has 51 MW waiting, more than Birmingham Selly Oak's 0 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.