CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bolton North East

MP: Kirith Entwistle (Labour) England Data to July 2026

Bolton North East has 2 MW of renewables running, enough for 600 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.3m across the constituency's 47,255 homes.

Ranks 544 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Union Court Storage FacilityInfinis Solar Developments Limited Battery 4.8 MW Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 11821/21

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Bolton North East 0.2 MW1.6 MWnot visible
Bury South 0.4 MW0 MWnot visible
Bolton South and Walkden 3.6 MW5 MWnot visible
Bolton West 0.6 MW2.2 MWnot visible
Bury North 0 MW0 MWnot visible
Rossendale and Darwen 0.3 MW75 MWnot visible

Bolton South and Walkden next door has 3.6 MW waiting, more than Bolton North East's 0.2 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.