Bolton North East
Bolton North East has 2 MW of renewables running, enough for 600 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.3m across the constituency's 47,255 homes.
Ranks 544 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Union Court Storage FacilityInfinis Solar Developments Limited | Battery | 4.8 MW | Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 11821/21 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Bolton North East | 0.2 MW | 1.6 MW | not visible |
| Bury South | 0.4 MW | 0 MW | not visible |
| Bolton South and Walkden | 3.6 MW | 5 MW | not visible |
| Bolton West | 0.6 MW | 2.2 MW | not visible |
| Bury North | 0 MW | 0 MW | not visible |
| Rossendale and Darwen | 0.3 MW | 75 MW | not visible |
Bolton South and Walkden next door has 3.6 MW waiting, more than Bolton North East's 0.2 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call