CONSTITUENCY BRIEFING · ENERGYMAP.APP
Woking
Woking has 1.9 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 700 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,437 homes.
Ranks 348 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Mclaren Technology Centre, Chertsey Road - Solar PanelsMcLaren Group Limited | Solar | 2.6 MW900 homes | Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PLAN/2025/0678 |
| Kestrel Way - Solar PanelsDigital Realty | Solar | 1.5 MW500 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PLAN/2024/0010 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Woking | 1.9 MW | 0 MW | not visible |
| Guildford | 1.1 MW | 0 MW | not visible |
| Surrey Heath | 0 MW | 0 MW | not visible |
| Runnymede and Weybridge | 0.6 MW | 1.8 MW | not visible |
Woking has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.