CONSTITUENCY BRIEFING · ENERGYMAP.APP
Vale of Glamorgan
Vale of Glamorgan has 123 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 45,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,054 homes.
Ranks 48 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Castle Road, Burton - Battery Energy Storage SystemRewe 7 Limited | Battery | 440 MW | Waiting 14 months for a planning decisionWho can move it: Vale of Glamorgan Council · planning ref 2025/00525/FUL |
| Aberthaw Battery Energy Storage SystemAberthaw Energy Limited | Battery | 249 MW | Still in the grid queue review — no firm connection date yetWho can move it: the grid operator (NESO) · earliest connection 2028 · planning ref 2025/01282/FUL |
| Vianshill Farm, Parc Dyffryn - Solar Farm & Battery StorageCenin Renewables Limited | Solar | 65 MW24,000 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3267575 |
| Pancross & Oaklands Solar FarmInfinis | Solar | 50 MW18,000 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref DNS/3245503 |
| Pancross & Oaklands Solar FarmInfinis | Battery | 50 MW | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref DNS/3245504 |
| Land at Pen Onn - Solar FarmIolo Energy | Solar | 45 MW16,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3273713 |
| Parc Worlton Solar FarmLightrock Power | Solar | 42 MW15,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref CAS-02112-T2N0G8 |
| East Aberthaw - Solar farmLow Carbon UK Solar Investment Co Limited | Solar | 35 MW13,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref CAS-01391-M3G6Q9 |
| Aston Martin Lagonda, Llanmaes - Solar Pv PanelsAston Martin Lagonda | Solar | 6 MW2,200 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/00617/FUL |
Plus 1 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Vale of Glamorgan | 123 MW | 74 MW | not visible |
| Cardiff South and Penarth | 25 MW | 12 MW | not visible |
| Cardiff West | 0 MW | 0 MW | not visible |
| Bridgend | 0.8 MW | 28 MW | not visible |
| Pontypridd | 41 MW | 42 MW | not visible |
Vale of Glamorgan has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call