Stockton West

MP: Matt Vickers (Conservative) England Data to July 2026

Stockton West has 161 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 58,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.5m across the constituency's 38,074 homes. There is also 22 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 30 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Byers Gill Solar FarmJBM Solar Projects Limited Solar 180 MW65,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010139
The Carrs - Meadow Farm Energy storage facilityBayWa r.e. Battery 57 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0752/FUL
Gately Moor Reservoir, Redmarshall - Solar Farm & Battery StorageCanadian Solar & Novergy Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/1499/FUL
Long Pasture Farm, Little Stainton - Solar FarmElectric Works Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01329/FUL
California Farm - Solar Farm & Battery StorageInfinis Solar Developments Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/1511/FUL
Long Pasture Farm, Little Stainton - Solar FarmElectric Works Battery 40 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01329/FUL
Letch Lane - Solar FarmAnesco Limited Solar 11 MW3,900 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/2290/FUL

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Stockton West 161 MW36 MWnot visible
Middlesbrough South and East Cleveland 50 MW5 MWnot visible
Middlesbrough and Thornaby East 0.5 MW0.2 MWnot visible
Richmond and Northallerton 111 MW71 MWnot visible
Darlington 84 MW6.2 MWnot visible
Newton Aycliffe and Spennymoor 47 MW45 MWnot visible

Stockton West has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.