CONSTITUENCY BRIEFING · ENERGYMAP.APP

Richmond and Northallerton

MP: Rishi Sunak (Conservative) England Data to July 2026

Richmond and Northallerton has 111 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 40,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 40,947 homes.

Ranks 58 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mowbray Battery Energy Storage StationMowbray Energy Park Limited Battery 1,000 MW Waiting 19 months for a planning decisionWho can move it: North Yorkshire Council · planning ref ZB24/02455/HYB
South Lowfields FarmLightsource BP Solar 50 MW18,000 homes Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 19/01882/FUL
Os Field 6800 Fence Dike Lane - Solar FarmLightrock Power Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/01362/FUL
Brompton Solar Farm - Solar FarmEnergyline Limited Solar 39 MW14,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ZD25/00038/FULL
Darlington Road, Skeeby - Battery Energy StorageAtrato Onsite Energy / Harmony Energy Battery 35 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ZD23/00342/FULL
East Cowton Solar FarmGreen Nation Solar Energy Solar 31 MW11,000 homes Waiting 13 months for a planning decisionWho can move it: North Yorkshire Council · planning ref ZB25/01134/FUL
Tunstall & East Appleton Solar Farm - Solar FarmEnviromena Solar 24 MW8,500 homes Waiting 13 months for a planning decisionWho can move it: North Yorkshire Council · planning ref ZD25/00369/FULL
Cross Rein Bank Solar Farm - Solar FarmPS Renewables Limited Solar 19 MW6,900 homes Waiting 14 months for a planning decisionWho can move it: North Yorkshire Council · planning ref ZB25/00887/FUL
Broken Scar Water Treatment Works Solar FarmNorthumbrian Water Limited Solar 9 MW3,300 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/00041/FULL

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Richmond and Northallerton 111 MW71 MWnot visible
Scarborough and Whitby 32 MW0 MWnot visible
Thirsk and Malton 7.2 MW20 MWnot visible
Middlesbrough South and East Cleveland 50 MW5 MWnot visible
Stockton West 161 MW36 MWnot visible
Darlington 84 MW6.2 MWnot visible

Stockton West next door has 161 MW waiting, more than Richmond and Northallerton's 111 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.