Staffordshire Moorlands

MP: Dame Karen Bradley (Conservative) England Data to July 2026

Staffordshire Moorlands has 13 MW of renewables running, enough for 4,900 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.5m across the constituency's 37,742 homes. A 99 MW battery was refused planning here in 2025; while discharging it could have supplied about 347,000 homes.

Ranks 510 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Cellarhead Substation, Rownall Road - Battery Energy FacilityC&S Energy Limited Battery 400 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SMD/2022/0444
Cellarhead Substation, Rownall Road - Battery Storage FacilityS & C Energy Limited Battery 400 MW Waiting 2.5 years for a planning decisionWho can move it: Staffordshire Moorlands Council · planning ref SMD/2024/0055
Leek Road, Werrington - Battery Energy StorageMasdar Arlington Energy Battery 300 MW Applied in 2025, still waiting for a decisionWho can move it: Staffordshire Council · planning ref SMD/2025/0354
Newfields Farm, Rownall Road - Battery Energy StorageREPD Limited Battery 100 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SMD/2024/0556
Adj New House Farm, Luzlow Lane - Battery Energy StorageYLEM (BESS) South Limited Battery 99 MW Refused by Staffordshire Moorlands Council in 2025Who can move it: Staffordshire Moorlands Council · planning ref SMD/2024/0568
Armshead Farm, Armshead Road - Battery Energy Storage FacilityConrad Energy (Developments) Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SMD/2022/0574
Brown Edge - Battery StorageAnesco Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SMD/2022/0076
Draycott Cross Road - Battery Storage SystemBalance Power Projects Limited Battery 40 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref SMD/2023/0263

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Staffordshire Moorlands 0.4 MW13 MWnot visible
Derbyshire Dales 16 MW56 MWnot visible
Burton and Uttoxeter 3 MW58 MWnot visible
Stoke-on-Trent South 115 MW14 MWnot visible
Stoke-on-Trent Central 1.6 MW0 MWnot visible
Stoke-on-Trent North 2.1 MW0 MWnot visible

Stoke-on-Trent South next door has 115 MW waiting, more than Staffordshire Moorlands's 0.4 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.