CONSTITUENCY BRIEFING · ENERGYMAP.APP

St Ives

MP: Andrew George (Liberal Democrat) England Data to July 2026

St Ives has 1.1 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,358 homes.

Ranks 410 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Trevarthian Farmhouse - Solar PV Farm & Battery Energy StorageTrevarthian Renewables Limited Solar 50 MW18,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA25/04503

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
St Ives 1.1 MW24 MWnot visible
Camborne and Redruth 35 MW61 MWnot visible

Camborne and Redruth next door has 35 MW waiting, more than St Ives's 1.1 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call