CONSTITUENCY BRIEFING · ENERGYMAP.APP

Camborne and Redruth

MP: Perran Moon (Labour) England Data to July 2026

Camborne and Redruth has 35 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 13,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,696 homes.

Ranks 167 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
The Coach House, Gwinear Lane - Speedwell Solar FarmStatKraft Solar 40 MW15,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/09696
Copper Bottom Solar Farm Ground-Mounted Solar PV ArrayAura Power Storage Solutions Solar 30 MW11,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA22/06139
Roddas, The Creamery - Solar Photovoltaic ArrayRoddas Solar 2.6 MW1,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/00424
Loggans Roundabout, Loggans Road - Solar FarmBauer Group Solar 2.5 MW900 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA24/02723
Treliever Cross Research Fields, Longdowns - Wind TurbineUniversity of Exeter Onshore wind 1 MW900 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA24/09072

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Camborne and Redruth 35 MW61 MWnot visible
St Ives 1.1 MW24 MWnot visible
Truro and Falmouth 80 MW99 MWnot visible

Truro and Falmouth next door has 80 MW waiting, more than Camborne and Redruth's 35 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call