CONSTITUENCY BRIEFING · ENERGYMAP.APP

South Leicestershire

MP: Alberto Costa (Conservative) England Data to July 2026

South Leicestershire has 125 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 45,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,391 homes. There is also 30 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 47 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Swinford Energy Park - Energy Park Facility & Battery StorageNatPower UK Battery 1,000 MW Applied in 2025, still waiting for a decisionWho can move it: Harborough Council · planning ref 25/00550/OUT
Normanton Energy Reserve - Battery StorageExagen SPVO2 Limited Battery 500 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/1204/FUL
Soars Lodge Farm, Foston Lane - Solar FarmSoars Solar Limited Solar 50 MW18,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0734/FUL
Desford Road, ThurlastonElgin Energy EsCo Solar 40 MW15,000 homes Approved 8 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 18/0242/FUL
Hinckley Road - Solar FarmCapital Dynamics Limited Solar 40 MW15,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/01242/FUL
Lychgate Lane, Aston Flamville - Solar FarmElgin Energy ES Co Limited Solar 20 MW7,300 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 22/0048/FUL
Hill Farm - Solar ParkHill Farm Solar Ltd Solar 20 MW7,300 homes Waiting 4.7 years for a planning decisionWho can move it: Blaby Council · planning ref 21/1386/FUL
Swinford Wind FarmVattenfall Solar 20 MW7,300 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/01853/FUL

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
South Leicestershire 125 MW56 MWnot visible
Hinckley and Bosworth 80 MW30 MWnot visible
Daventry 130 MW77 MWnot visible
Rugby 77 MW25 MWnot visible
Harborough, Oadby and Wigston 0.2 MW8.7 MWnot visible
Leicester South 0.3 MW0 MWnot visible

Daventry next door has 130 MW waiting, more than South Leicestershire's 125 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.