Norwich North

MP: Alice Macdonald (Labour (Co-op)) England Data to July 2026

Norwich North has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,374 homes.

Ranks 486 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Glebe Horsford - Solar FarmPathfinder Clean Energy UKDev Limited Solar 18 MW6,500 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/2395

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Norwich North 0.5 MW0 MWnot visible
South Norfolk 104 MW37 MWnot visible
Norwich South 1 MW1.9 MWnot visible
Broadland and Fakenham 46 MW100 MWnot visible

South Norfolk next door has 104 MW waiting, more than Norwich North's 0.5 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.