Northampton South

MP: Mike Reader (Labour) England Data to July 2026

Northampton South has 10 MW of renewables running, enough for 3,600 homes over a year, and nothing large waiting in the planning queue. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,237 homes.

Ranks 428 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Sainsburys, Style Way - Solar PanelsSainsburys Supermarkets Limited Solar 4.5 MW1,600 homes Applied in 2026, still waiting for a decisionWho can move it: West Northamptonshire Council · planning ref 2026/2336/PA

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Northampton South 0.9 MW10 MWnot visible
South Northamptonshire 104 MW85 MWnot visible
Northampton North 0.5 MW0 MWnot visible
Daventry 130 MW77 MWnot visible

Daventry next door has 130 MW waiting, more than Northampton South's 0.9 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.