Llanelli has 106 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 39,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 40,821 homes.

Ranks 61 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Tycroes Solar FarmSpring Dev 2 Solar 40 MW15,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3227364
Brynrhyd Solar FarmCapital Dynamics Limited Solar 36 MW13,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3260565
Pencoed Ganol Farm, Pendderi Road - Solar PanelsWindel Solar 11 Limited Solar 35 MW13,000 homes Applied in 2025, still waiting for a decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-04012-T8Y8D2
Llangennech SolarVoltalia UK Solar 30 MW11,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DNS/3213164
Heol Aur, Dafen Industrial Estate - Battery Storage SystemWestfa Limited Battery 25 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/09340
Glyngwernen Farm, Uchaf Fawr - Solar FarmBartypower Limited Solar 8.4 MW3,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PL/08017

Plus 4 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Llanelli 106 MW44 MWnot visible
Gower 0 MW62 MWnot visible
Caerfyrddin 7 MW157 MWnot visible

Llanelli has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.