CONSTITUENCY BRIEFING · ENERGYMAP.APP

Hamilton and Clyde Valley

MP: Imogen Walker (Labour) Scotland Data to July 2026

Hamilton and Clyde Valley was paid £170k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 2.1 days. A further 2.1 MW of approved clean power (all solar) is still waiting to be built here: enough to supply a year's electricity to 700 homes. A 50 MW battery approved at Cornhills Farm, Muttonhole Road in 2025 would store power that is currently wasted; it has not been built.

Ranks 341 of 650 for clean power approved and not built; 18 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Coalburn Energy - Battery StorageAlcemi Storage Development Limited Battery 500 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref ECU00003458
Rogerhill Solar and Battery Energy Storage SystemGreen Switch Capital Limited Battery 100 MW Waiting 19 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref P/25/0018
Rogerhill Solar and Battery Energy Storage SystemGreen Switch Capital Limited Solar 100 MW36,000 homes Waiting 19 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref P/25/0018
Cornhills Farm, Muttonhole Road - Battery StorageBig Battery (Sheriff Faulds Farm 1) Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/23/1613

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Hamilton and Clyde Valley 2.1 MW61 MW£170k
Dumfriesshire, Clydesdale and Tweeddale 913 MW1,451 MW£15m
Kilmarnock and Loudoun 82 MW283 MW£900k
East Kilbride and Strathaven 38 MW264 MW£3.1m
Motherwell, Wishaw and Carluke 80 MW215 MW£2.4m
Rutherglen 1.5 MW0 MWnot visible

Dumfriesshire, Clydesdale and Tweeddale next door has 913 MW waiting, more than Hamilton and Clyde Valley's 2.1 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.