Filton and Bradley Stoke
Filton and Bradley Stoke has 8.7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,100 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,325 homes.
Ranks 232 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Airbus UK Industrial Complex - Solar panelsCustom Solar Limited | Solar | 3.1 MW1,100 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P24/00385/PNRE |
| Folly Brook Road, Emersons Green - Solar PanelsJJ Foodservice Limited | Solar | 1 MW400 homes | Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P22/05190/PNRE |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Filton and Bradley Stoke | 8.7 MW | 20 MW | not visible |
| Bristol North East | 0 MW | 0 MW | not visible |
| Bristol North West | 5.6 MW | 43 MW | not visible |
| Thornbury and Yate | 203 MW | 147 MW | not visible |
Thornbury and Yate next door has 203 MW waiting, more than Filton and Bradley Stoke's 8.7 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call