CONSTITUENCY BRIEFING · ENERGYMAP.APP

Exmouth and Exeter East

MP: David Reed (Conservative) England Data to July 2026

Exmouth and Exeter East has 150 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 55,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,783 homes.

Ranks 34 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Saundercroft Farm - Battery Energy Storage SystemExeter Storage Limited (Statera Energy) Battery 290 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0962/MFUL
Exeter Substation, Broadclyst - Battery Energy StorageIsland Green Power Battery 125 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/1150/MFUL
National Grid Substation - Battery Energy Storage SystemPenso Power (BW ESS) Battery 100 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/0063/MFUL
Blackhill Quarry, Woodbury - Battery Energy Storage FacilityClinton Devon Estates Battery 60 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/2546/MFUL
Saundercroft Road, Broadclyst - Battery Energy Storage SystemPivoted Power Llp Battery 57 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/2664/MFUL
Higher Bagmore Farm, Ebford Lane -Battery Energy Storage SystemEnviromena Battery 50 MW Waiting 13 months for a planning decisionWho can move it: East Devon Council · planning ref 25/1338/MFUL
Rutton Farm, Whimple - Horton Solar FarmAura Power Developments Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/0783/MFUL
Paytherden Solar Farm (Peradon)Lightrock Power Limited Solar 49 MW18,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 21/3120/MFUL
Ford Oaks Solar & Green Infrastructure FacilityLow Carbon Alliance / Taiyo Power & Storage Solar 30 MW11,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 22/0990/MFUL
Higher Hawkerland Farm, Sidmouth Road - Solar FarmSpring Dev 09 Limited Solar 18 MW6,500 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/2409/MFUL
Kerswell Barton Farm, Broadclyst - Solar PanelsMJ Quinn Integrated Services Limited Solar 16 MW5,900 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/0467/MFUL

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Exmouth and Exeter East 150 MW50 MWnot visible
Exeter 2.8 MW0 MWnot visible
Honiton and Sidmouth 39 MW77 MWnot visible
Central Devon 11 MW41 MWnot visible

Exmouth and Exeter East has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.