CONSTITUENCY BRIEFING · ENERGYMAP.APP

Edmonton and Winchmore Hill

MP: Kate Osamor (Labour (Co-op)) England Data to July 2026

Edmonton and Winchmore Hill has 1.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,393 homes.

Ranks 398 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
North London Heat and Power (Edmonton EcoPark Replacement)North London Waste Authority (NLWA) EfW Incineration 70 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref EN010071

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Edmonton and Winchmore Hill 1.2 MW0.2 MWnot visible
Tottenham 0 MW0 MWnot visible
Walthamstow 0 MW0 MWnot visible
Chingford and Woodford Green 0.2 MW0 MWnot visible
Southgate and Wood Green 0 MW0 MWnot visible
Enfield North 3.7 MW0 MWnot visible

Enfield North next door has 3.7 MW waiting, more than Edmonton and Winchmore Hill's 1.2 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 1 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.