CONSTITUENCY BRIEFING · ENERGYMAP.APP

Doncaster Central

MP: Sally Jameson (Labour (Co-op)) England Data to July 2026

Doncaster Central has 62 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 23,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.5m across the constituency's 49,026 homes.

Ranks 108 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mere Flats Solar FarmNextPower UK Solar 56 MW20,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01978/FULM
Cutts Bros, Wharf Road - Battery Storage FacilityNewton Energi Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00841/FUL
BH Energy Gap - Energy Recovery FacilityBH Energy Gap Limited EfW Incineration 34 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 20/01774/TIPA
Mere Flats Solar FarmNextPower UK Battery 16 MW Waiting 3.9 years for a planning decisionWho can move it: Doncaster Council · planning ref 22/01978/FULM
J3 Business Park - Battery Storage FacilityForepower Limited Battery 16 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/01072/FUL
J3 Business Park - Battery Energy Storage FacilityForepower Limited Battery 10 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 22/02368/FUL

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Doncaster Central 62 MW4.2 MWnot visible
Bassetlaw 114 MW85 MWnot visible
Rother Valley 49 MW24 MWnot visible
Rawmarsh and Conisbrough 2.2 MW0 MWnot visible
Doncaster East and the Isle of Axholme 83 MW146 MWnot visible
Doncaster North 3.8 MW21 MWnot visible

Bassetlaw next door has 114 MW waiting, more than Doncaster Central's 62 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.