Dewsbury and Batley has 50 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.5m across the constituency's 37,698 homes.

Ranks 141 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Low Farm, Flockton - Solar Photovoltaic FarmDowning LLP Solar 50 MW18,000 homes Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2021/62/93644/E

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Dewsbury and Batley 50 MW0 MWnot visible
Ossett and Denby Dale 52 MW0 MWnot visible
Huddersfield 5.1 MW0 MWnot visible
Spen Valley 0.3 MW0 MWnot visible
Leeds South West and Morley 0.7 MW5 MWnot visible

Ossett and Denby Dale next door has 52 MW waiting, more than Dewsbury and Batley's 50 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.