Cowdenbeath and Kirkcaldy

MP: Melanie Ward (Labour) Scotland Data to July 2026

Cowdenbeath and Kirkcaldy has 70 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 25,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,645 homes. There is also 38 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 98 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mossmorran Battery StorageGresham House Devco Pipeline Battery 300 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004985
Gleniston, Auchtertool - Battery Storage FacilityHarmony Energy Limited Battery 50 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/02323/FULL
South Pargillis - Battery StorageInfinis Energy Services Limited Battery 42 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/03945/FULL
Glenniston Farm, Auchtertool - Solar FarmLocogen Consulting Limited Solar 39 MW14,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/02598/FULL
STOR Field 9Capbal Battery 37 MW Cannot connect to the grid until 2029, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2029 · planning ref 18/01583/PPP
Parkend Crossgates - Solar Panels & Battery StorageGreentech Projects Holding UK Limited Solar 30 MW11,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/03982/FULL
Glenniston Farm, Auchtertool - Solar FarmLocogen Consulting Limited Battery 10 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/02598/FULL
Parkend Crossgates - Solar Panels & Battery StorageGreentech Projects Holding UK Limited Battery 9 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/03982/FULL

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Cowdenbeath and Kirkcaldy 70 MW39 MWnot visible
Dunfermline and Dollar 36 MW5.1 MWnot visible
Glenrothes and Mid Fife 121 MW48 MWnot visible

Glenrothes and Mid Fife next door has 121 MW waiting, more than Cowdenbeath and Kirkcaldy's 70 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.