CONSTITUENCY BRIEFING · ENERGYMAP.APP

Chichester

MP: Jess Brown-Fuller (Liberal Democrat) England Data to July 2026

Chichester has 19 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 6,800 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.2m across the constituency's 45,526 homes.

Ranks 203 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mundham, Runcton Lane - Solar FarmBNRG Renewables Limited Solar 30 MW11,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01859/FUL
Ferry Farm - Solar arrayBNRG & Lanlink Estates Limited Solar 11 MW4,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/01816/FULEIA
Sefter Farm, Pagham Road - Solar PanelsBarfoots Of Botley Limited Solar 2 MW700 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/60/23/PL
Natures Way Food, Chichester Road - Solar PanelsLandlink Estates Limited Solar 1.8 MW700 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01128/PA14J
Baker Barracks Solar DevelopmentDefence Estates Infrastructure Organisation Solar 1.5 MW500 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 20/03047/FULEIA
Chichester Food Park, Runcton Unit - Solar PanelsLandlink Estates Limited Solar 1.3 MW500 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/01127/PA14J

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Chichester 19 MW75 MWnot visible
Bognor Regis and Littlehampton 0.7 MW22 MWnot visible
Arundel and South Downs 0 MW21 MWnot visible
Havant 1.5 MW0 MWnot visible
East Hampshire 78 MW56 MWnot visible

East Hampshire next door has 78 MW waiting, more than Chichester's 19 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.