CONSTITUENCY BRIEFING · ENERGYMAP.APP
Birmingham Yardley
Birmingham Yardley has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,373 homes.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Hay Hall Road Energy Recovery FacilityHay Hall Bio Power | Advanced Conversion Technologies | 25 MW | Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2018/09425/PA |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Birmingham Yardley | 0 MW | 0 MW | not visible |
| Solihull West and Shirley | 1.8 MW | 0 MW | not visible |
| Meriden and Solihull East | 1.9 MW | 0 MW | not visible |
| Birmingham Hall Green and Moseley | 2.1 MW | 0 MW | not visible |
| Birmingham Ladywood | 1.9 MW | 0 MW | not visible |
| Birmingham Hodge Hill and Solihull North | 1.1 MW | 0 MW | not visible |
Birmingham Hall Green and Moseley next door has 2.1 MW waiting, more than Birmingham Yardley's 0 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 1 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call
Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.