CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bicester and Woodstock

MP: Calum Miller (Liberal Democrat) England Data to July 2026

Bicester and Woodstock has 112 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 41,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,359 homes.

Ranks 55 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Botley West, Botley - Botley West Solar ProjectPhotovolt Development Partners / SolarFive Solar 840 MW305,000 homes Waiting 21 months for a planning decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects) · planning ref EN010147
Woodstock Road, Yarnton - Battery Energy Storage SystemRenewable Connections Developments Limited Battery 52 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/02872/F
Tar Solar FarmBluefield Renewable Developments Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 21/03711/FUL
Manor Farm, Noke - Solar FarmGreen Nation Solar 45 MW16,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01682/F
Pool Farm, Mill Lane, Stratton - Solar FarmJBM Solar Projects Limited Solar 44 MW16,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/03873/F
Bicester Road, Launton - Battery Energy StoragePowersun Limited Battery 40 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00949/F
Tar Solar FarmBluefield Renewable Developments Limited Battery 40 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/03261/FUL
Aurora Solar FarmLow Carbon UK Solar Investment Company Solar 32 MW12,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/02516/FUL
Ray Valley Solar FarmLow Carbon Solar 19 MW6,900 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 20/00285/F
Aurora Solar FarmLow Carbon UK Solar Investment Company Battery 18 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 19/02516/FUL
Station Road, Ardley - Solar Farm & Battery Energy Storage SystemValencia Waster Management Limited Solar 10 MW3,800 homes Waiting 2.5 years for a planning decisionWho can move it: Cherwell Council · planning ref MW.0018/24
Blenheim Net Zero EstateVanburgh Unit Trust Solar 5 MW1,800 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 20/01817/FUL

Plus 4 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Bicester and Woodstock 112 MW80 MWnot visible
Witney 48 MW61 MWnot visible
Banbury 10 MW20 MWnot visible
Henley and Thame 151 MW35 MWnot visible
Oxford West and Abingdon 2.7 MW0 MWnot visible
Mid Buckinghamshire 136 MW7.8 MWnot visible

Henley and Thame next door has 151 MW waiting, more than Bicester and Woodstock's 112 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.