Airdrie and Shotts
Airdrie and Shotts was paid £2.3m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 31 days. A further 24 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 20,000 homes. A 300 MW battery approved at Newarthill Energy Park in 2025 would store power that is currently wasted; it has not been built.
Ranks 185 of 650 for clean power approved and not built; 14 of 19 among seats with visible switch-off payments.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Newarthill Energy ParkGeocore Limited | Battery | 300 MW | Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref ECU00004953 |
| North Lanrigg Energy StorageNorth Lanrigg Battery Storage Limited | Battery | 200 MW | Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2028 · planning ref ECU00005166 |
| Fernishaw Solar Farm & Battery Energy Storage FacilityElgin Energy (EEB67) | Solar | 75 MW27,000 homes | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004871 |
| Locks Street, Coatdyke - Battery Energy Storage SystemsBluestone Energy | Battery | 45 MW | Applied in 2025, still waiting for a decisionWho can move it: North Lanarkshire Council · planning ref 25/00935/FUL |
| Biggar Road, Cleland - Battery Energy Storage SystemStarlight Energy SPV 1 Limited | Battery | 30 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00810/FUL |
| Torrance Wind Farm Extension 2Infinergy | Onshore wind | 26 MW23,000 homes | Refused by North Lanarkshire Council in 2025Who can move it: North Lanarkshire Council · planning ref 23/00256/FUL |
| Fernishaw Solar Farm & Battery Energy Storage FacilityElgin Energy (EEB67) | Battery | 25 MW | Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004871 |
| West Benhar Road, Eastfield, Harthill - Wind TurbinesPremarket Developments Limted | Onshore wind | 20 MW17,000 homes | Waiting 12 months for a planning decisionWho can move it: North Lanarkshire Council · planning ref 25/00637/FUL |
| Forrestfield Wind FarmWest Cost Energy | Onshore wind | 13 MW12,000 homes | Waiting 11.1 years for a planning decisionWho can move it: North Lanarkshire Council · earliest connection 2026 · planning ref 15/01411/FUL |
| Dewshill Wind FarmWind Estate (UK) Ltd | Onshore wind | 9 MW7,900 homes | Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00379/FUL |
| Brownhill FarmWind Estate | Onshore wind | 8.4 MW7,300 homes | Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 20/00504/FUL |
Plus 11 smaller projects — see the full seat page.
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Airdrie and Shotts | 24 MW | 82 MW | £2.3m |
| Livingston | 118 MW | 116 MW | not visible |
| Bathgate and Linlithgow | 46 MW | 9.8 MW | not visible |
| Motherwell, Wishaw and Carluke | 80 MW | 215 MW | £2.4m |
| Coatbridge and Bellshill | 0.6 MW | 0.2 MW | not visible |
| Cumbernauld and Kirkintilloch | 1.2 MW | 0 MW | not visible |
Livingston next door has 118 MW waiting, more than Airdrie and Shotts's 24 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call