CONSTITUENCY BRIEFING · ENERGYMAP.APP

Airdrie and Shotts

MP: Kenneth Stevenson (Labour) Scotland Data to July 2026

Airdrie and Shotts was paid £2.3m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 31 days. A further 24 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 20,000 homes. A 300 MW battery approved at Newarthill Energy Park in 2025 would store power that is currently wasted; it has not been built.

Ranks 185 of 650 for clean power approved and not built; 14 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Newarthill Energy ParkGeocore Limited Battery 300 MW Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO) · earliest connection 2029 · planning ref ECU00004953
North Lanrigg Energy StorageNorth Lanrigg Battery Storage Limited Battery 200 MW Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2028 · planning ref ECU00005166
Fernishaw Solar Farm & Battery Energy Storage FacilityElgin Energy (EEB67) Solar 75 MW27,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004871
Locks Street, Coatdyke - Battery Energy Storage SystemsBluestone Energy Battery 45 MW Applied in 2025, still waiting for a decisionWho can move it: North Lanarkshire Council · planning ref 25/00935/FUL
Biggar Road, Cleland - Battery Energy Storage SystemStarlight Energy SPV 1 Limited Battery 30 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00810/FUL
Torrance Wind Farm Extension 2Infinergy Onshore wind 26 MW23,000 homes Refused by North Lanarkshire Council in 2025Who can move it: North Lanarkshire Council · planning ref 23/00256/FUL
Fernishaw Solar Farm & Battery Energy Storage FacilityElgin Energy (EEB67) Battery 25 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00004871
West Benhar Road, Eastfield, Harthill - Wind TurbinesPremarket Developments Limted Onshore wind 20 MW17,000 homes Waiting 12 months for a planning decisionWho can move it: North Lanarkshire Council · planning ref 25/00637/FUL
Forrestfield Wind FarmWest Cost Energy Onshore wind 13 MW12,000 homes Waiting 11.1 years for a planning decisionWho can move it: North Lanarkshire Council · earliest connection 2026 · planning ref 15/01411/FUL
Dewshill Wind FarmWind Estate (UK) Ltd Onshore wind 9 MW7,900 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00379/FUL
Brownhill FarmWind Estate Onshore wind 8.4 MW7,300 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref 20/00504/FUL

Plus 11 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Airdrie and Shotts 24 MW82 MW£2.3m
Livingston 118 MW116 MWnot visible
Bathgate and Linlithgow 46 MW9.8 MWnot visible
Motherwell, Wishaw and Carluke 80 MW215 MW£2.4m
Coatbridge and Bellshill 0.6 MW0.2 MWnot visible
Cumbernauld and Kirkintilloch 1.2 MW0 MWnot visible

Livingston next door has 118 MW waiting, more than Airdrie and Shotts's 24 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.