CONSTITUENCY BRIEFING · ENERGYMAP.APP

The Wrekin

MP: Mark Pritchard (Conservative) England Data to July 2026

The Wrekin has 221 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 80,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,662 homes.

Ranks 16 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Myttons Solar FarmJBM Solar Projects Limited Solar 50 MW18,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref TWC/2020/0851
High Ercall Solar FarmAssured Asset Solar 1 Limited Solar 50 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref TWC/2023/0064
The Old Airfield - Solar FarmPeridot Solar Limited Solar 49 MW18,000 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01866/FUL
New Works Lane - Solar FarmGreentech Solar 30 MW11,000 homes Waiting 5.0 years for a planning decisionWho can move it: Telford and Wrekin Council · planning ref TWC/2021/0737
Steeraway Farm - Solar FarmEnviromena Solar 30 MW11,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref TWC/2021/1071
Twitch Hill, Cheswell Grange Farm - Solar Farm & Battery StorageEthical Power Solar 25 MW9,100 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref TWC/2021/1225
County Lane - Solar farmBoultbee Brooks Renewable Energy Limited Solar 16 MW5,800 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01816/FUL
Tiddiecross Lane, Charlton - Tiddiecross Solar Farm & Battery StorageBoultbee Brooks Renewables Walkford Moor Limited Solar 14 MW5,100 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref TWC/2024/0909
Hollins Lane - Battery Energy StorageHydrock Consultants Limited Battery 13 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00223/FUL
Albrighton Substation, Beamish Lane - Battery StorageFig Power (part of Hydrock) Battery 7 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/04541/FUL

Plus 2 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
The Wrekin 221 MW75 MWnot visible
Shrewsbury 25 MW37 MWnot visible
South Shropshire 112 MW78 MWnot visible
Kingswinford and South Staffordshire 2.5 MW11 MWnot visible
Telford 3.9 MW1.2 MWnot visible
Stafford 0.9 MW0 MWnot visible

The Wrekin has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.