St Helens North
St Helens North has 1 MW of renewables running, enough for 900 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,922 homes.
Ranks 439 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Holiday Moss Landfill Site, Reeds Brow - Battery StorageBiffa Waste Services Limited | Battery | 3 MW | Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/2022/0627/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| St Helens North | 0.9 MW | 1 MW | not visible |
| St Helens South and Whiston | 2.1 MW | 0 MW | not visible |
| Warrington North | 11 MW | 0 MW | not visible |
| Leigh and Atherton | 0 MW | 0.5 MW | not visible |
| Makerfield | 2.2 MW | 0 MW | not visible |
| Knowsley | 1.5 MW | 0.8 MW | not visible |
Warrington North next door has 11 MW waiting, more than St Helens North's 0.9 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call