CONSTITUENCY BRIEFING · ENERGYMAP.APP

St Austell and Newquay

MP: Noah Law (Labour) England Data to July 2026

St Austell and Newquay has 11 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 8,900 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,478 homes.

Ranks 222 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Indian Queens National Grid Substation, Domelick Hill - Battery StorageEDF Energy Renewables (merged with Pivot Power) Battery 50 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/06527
Indian Queens Sub station, Carne Hill - Battery Energy StorageRenewable Connections Development Limited Battery 50 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/04504
Green Acres Farm, Scarcewater - Solar FarmEDF Renewables Solar 50 MW18,000 homes Waiting 24 months for a planning decisionWho can move it: Cornwall Council · planning ref PA24/05312
Burthy Row Farm, Trefullock Moor - Solar Farm & Battery StorageJBM Solar Projects Limited Solar 50 MW18,000 homes Waiting 3.4 years for a planning decisionWho can move it: Cornwall Council · planning ref PA23/01893
Indian Queens Sub-Station - Battery StoragePrime Energy Development Limited / Valero Energy / Sambar Power Battery 48 MW Cannot connect to the grid until 2027, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2027 · planning ref PA22/05961
Menear Road - Solar & Battery storageAnesco Limited Solar 18 MW6,400 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/09532
Mount Stamper Road, Treverbyn - Battery Energy StorageAldustria Energy Storage Battery 10 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA24/01713
Eden Project Geothermal Energy FacilityEGS Energy/Eden Project Limited Hot Dry Rocks (HDR) 7 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref PA10/04671
Tregorrick FarmE H Energy Limited Solar 6 MW2,200 homes Refused by Cornwall Council in 2023Who can move it: the planning appeal inspector · planning ref PA20/11504
Eden ProjectGood Energy Battery 5 MW Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA19/03137
Menear Road - Solar & Battery storageAnesco Limited Battery 5 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA23/09532

Plus 6 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
St Austell and Newquay 11 MW96 MWnot visible
Truro and Falmouth 80 MW99 MWnot visible
South East Cornwall 1.9 MW119 MWnot visible
North Cornwall 10 MW197 MWnot visible

Truro and Falmouth next door has 80 MW waiting, more than St Austell and Newquay's 11 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.