CONSTITUENCY BRIEFING · ENERGYMAP.APP

Selby

MP: Keir Mather (Labour) England Data to July 2026

Selby has 190 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 69,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,292 homes. There is also 34 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 23 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Eggborough Battery Energy Storage SystemSSE Renewables Ireland Limited Battery 550 MW Cannot connect to the grid until 2032, 7 years after it was approvedWho can move it: the grid operator (NESO) and National Grid · earliest connection 2032 · planning ref ZG2024/1306/FULM
Eggborough Power Station, Selby Road - Battery StorageEggborough Power Limited Battery 500 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2022/1105/FULM
Light Valley Solar, Selby Road - Solar FarmLight Valley Solar Limited ( Island Green Power) Solar 500 MW182,000 homes Applied in 2026, still waiting for a decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects) · planning ref EN0110012
Monk Fryston Battery StorageSSE Renewables Battery 320 MW Its grid connection date of 2025 has passed and it is still not generatingWho can move it: the grid operator (NESO) and National Grid · earliest connection 2025 · planning ref 2021/0789/FULM
Springfield Farm, Weeland Road - Battery Energy Storage FacilityNewton Energi Limited Battery 240 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ZG2024/0549/FULM
Springfield Farm, Hensall - Battery Energy Storage FacilityNewton Energi Limited Battery 240 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2023/0285/FULM
Rawfield Lane - Battery Energy Storage SystemHarmony Energy Limited Battery 200 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ZG2024/1317/FULM
Stocking Lane - Battery Energy FacilityNel Tiger Battery 200 MW Waiting 2.9 years for a planning decisionWho can move it: North Yorkshire Council · planning ref ZG2023/0938/FULM
Corner Of Weeland Road, Lunn Lane - Battery Storage FacilityNewton Energi Limited Battery 200 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ZG2023/1179/FULM
Helios Renewable Energy ProjectEnso Green Holdings D Limited Solar 190 MW69,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010140
Hales Lane - Battery Storage FacilityAura Power Battery 100 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2021/1089/FULM
Lakeside Energy Storage FacilityTag Energy UK Battery 100 MW Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 2020/1357/FULM

Plus 17 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Selby 190 MW49 MWnot visible
Normanton and Hemsworth 3.7 MW2.4 MWnot visible
Wakefield and Rothwell 3.4 MW0 MWnot visible
Leeds East 6.4 MW0 MWnot visible
Doncaster North 3.8 MW21 MWnot visible
Pontefract, Castleford and Knottingley 1.9 MW7.4 MWnot visible

Selby has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.