CONSTITUENCY BRIEFING · ENERGYMAP.APP
Plymouth Moor View
Plymouth Moor View has 5.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,057 homes.
Ranks 255 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Roborough Solar FarmRegener8 Power (Plymouth) | Solar | 2.6 MW1,000 homes | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 22/01922/FUL |
| Roborough Solar FarmRegener8 Power (South Hampshire) | Solar | 2.6 MW1,000 homes | Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 4072/22/FUL |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Plymouth Moor View | 5.5 MW | 4.1 MW | not visible |
| Plymouth Sutton and Devonport | 0.1 MW | 0 MW | not visible |
| South West Devon | 20 MW | 56 MW | not visible |
South West Devon next door has 20 MW waiting, more than Plymouth Moor View's 5.5 MW.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting