CONSTITUENCY BRIEFING · ENERGYMAP.APP

Mid Dorset and North Poole

MP: Vikki Slade (Liberal Democrat) England Data to July 2026

Mid Dorset and North Poole has 3.3 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,200 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,506 homes.

Ranks 293 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Mannington Battery Energy Storage SystemEDF Energy Renewables Battery 50 MW Its grid connection date of 2025 has passed and it is still not generatingWho can move it: the grid operator (NESO) and National Grid · earliest connection 2025 · planning ref 3/21/0137/FUL
Holt Road - Battery Energy StorageEDF Energy Renewables Battery 48 MW Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/FUL/2023/06578
Post Farm, Lytchett Minster - Battery Energy StorageS4N Lytchett Limited Battery 32 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref P/FUL/2023/02819
Canford Resource Park- Energy from Waste/CHPMVV Environment Limited EfW Incineration 30 MW Refused by Bournemouth, Christchurch and Poole Council in 2025Who can move it: Bournemouth, Christchurch and Poole Council · planning ref APP/23/00822/F
CanfordSyngas Products/ Canford Renewable Energy Ltd Advanced Conversion Technologies 10 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref APP/12/01559/F

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Mid Dorset and North Poole 3.3 MW90 MWnot visible
Poole 1.7 MW0 MWnot visible
Bournemouth West 0 MW0 MWnot visible
Christchurch 36 MW128 MWnot visible
North Dorset 97 MW94 MWnot visible
South Dorset 73 MW73 MWnot visible

North Dorset next door has 97 MW waiting, more than Mid Dorset and North Poole's 3.3 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call