Mid and South Pembrokeshire

MP: Henry Tufnell (Labour) Wales Data to July 2026

Mid and South Pembrokeshire has 9.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,486 homes.

Ranks 231 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Goldborough Road, Hundleton - Battery Energy StoragePembroke Green Limited (Enso Energy and Cero Generation) Battery 350 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0133/PA
Pembroke Power Station, Pwllcrochan - Battery StorageRWE Generation UK Plc Battery 350 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0600/PA
Pembroke Power Station, Pwllcrochan - Hydrogen Production FacilityRWE Generation UK Plc Hydrogen 110 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0372/PA
The Greenlink Converter Station - Lambeeth Battery Energy StorageSirius EcoDev Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0857/PA
Alleston Solar FarmStantec UK Limited Solar 30 MW11,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref CAS-03072-D7X6N7
White House FarmQair UK Solar 30 MW11,000 homes Applied in 2025, still waiting for a decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-03107-C5X9W1
Puma Energy Site - Hydrogen Generation FacilityH2 Energy Ecosystem UK Hydrogen 20 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/0448/PA
Pembroke Dockyard - Green Hydrogen Production FacilityHaush Limited Hydrogen 15 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/0916/PA
Dragon Energy Park - Wind FarmDragon LNG Onshore wind 14 MW13,000 homes Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref CAS-01859-K1M7Y6
Rhoscrowther - Turbine Wind FarmRhoscrowther Wind Farm Limited Onshore wind 13 MW11,000 homes Refused by the Welsh Government (it decides big energy projects) in 2022Who can move it: the Welsh Government (it decides big energy projects) · planning ref DNS/3261355
White House FarmQair UK Battery 12 MW Applied in 2025, still waiting for a decisionWho can move it: the Welsh Government (it decides big energy projects) · planning ref CAS-03107-C5X9W1
Blackberry Lane - Solar FarmWessex Solar Energy Solar 10 MW3,600 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/1022/PA

Plus 3 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Mid and South Pembrokeshire 9.5 MW193 MWnot visible
Caerfyrddin 7 MW157 MWnot visible
Ceredigion Preseli 1.7 MW114 MWnot visible

Mid and South Pembrokeshire has more approved-and-waiting capacity than any of its neighbouring seats.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.