CONSTITUENCY BRIEFING · ENERGYMAP.APP

Hartlepool

MP: Mr Jonathan Brash (Labour) England Data to July 2026

Hartlepool has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 19,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 40,930 homes.

Ranks 126 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Worset Lane - Battery Energy Storage SystemClearstone Energy Battery 200 MW Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2022/0263
Whelley Hill Farm, Worset Lane - Battery Energy StorageReliance Energy Limited Battery 50 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2022/0459
Worset Lane - Solar FarmCanadian Solar UK Solar 50 MW18,000 homes Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2020/0175
High Barnes Farm, Coal Lane - Solar FarmEnviromena Project Management UK Limited Solar 50 MW18,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2024/0180
Graythorpe Energy CentreGraythorp Energy EfW Incineration 50 MW Approved 6 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2019/0275
High Barnes Farm, Coal Lane - Battery StorageEnviromena Project Management UK Limited Battery 25 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref H/2024/0180

Plus 1 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Hartlepool 51 MW28 MWnot visible
Newton Aycliffe and Spennymoor 47 MW45 MWnot visible
Easington 102 MW33 MWnot visible
Stockton North 5.1 MW8 MWnot visible

Easington next door has 102 MW waiting, more than Hartlepool's 51 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.