CONSTITUENCY BRIEFING · ENERGYMAP.APP

Earley and Woodley

MP: Yuan Yang (Labour) England Data to July 2026

Earley and Woodley has 3.7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,300 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.6m across the constituency's 38,905 homes.

Ranks 281 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Suttons Park Avenue, Suttons Business Park - Solar PVBrakes Group Solar 1.3 MW500 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 231133

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Earley and Woodley 3.7 MW7 MWnot visible
Wokingham 48 MW0 MWnot visible
Reading West and Mid Berkshire 32 MW22 MWnot visible
Reading Central 0.4 MW0 MWnot visible
Henley and Thame 151 MW35 MWnot visible

Henley and Thame next door has 151 MW waiting, more than Earley and Woodley's 3.7 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.