Cambridge

MP: Daniel Zeichner (Labour) England Data to July 2026

Cambridge has 1.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,570 homes.

Ranks 378 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
St Bedes Inter-Church SchoolSolar Options for Schools Solar 1 MW400 homes Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 19/0136/C14P14

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Cambridge 1.5 MW0 MWnot visible
South Cambridgeshire 27 MW251 MWnot visible
St Neots and Mid Cambridgeshire 52 MW10 MWnot visible
Ely and East Cambridgeshire 145 MW257 MWnot visible

Ely and East Cambridgeshire next door has 145 MW waiting, more than Cambridge's 1.5 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 2 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call