Bangor Aberconwy
Bangor Aberconwy has 18 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 15,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,182 homes. There is also 182 MW of wind running here on the local network. If that gets switched off, no national record shows it.
Ranks 205 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Pant y MaenGresham House | Onshore wind | 18 MW15,000 homes | Approved 9 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/2015/0321 |
Compared with its neighbours
| Constituency | Approved, not built | Running | Paid to switch off |
|---|---|---|---|
| Bangor Aberconwy | 18 MW | 214 MW | not visible |
| Clwyd East | 0 MW | 1.8 MW | not visible |
| Clwyd North | 0 MW | 5 MW | not visible |
| Dwyfor Meirionnydd | 1.9 MW | 49 MW | not visible |
Bangor Aberconwy has more approved-and-waiting capacity than any of its neighbouring seats.
The rest of the briefing
- Every approval each project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call