Argyll, Bute and South Lochaber

MP: Brendan O'Hara (Scottish National Party) Scotland Data to July 2026

Argyll, Bute and South Lochaber was paid £1.7m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 21 days. A further 384 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 338,000 homes. A 56 MW battery approved at High Constellation Wind Farm in 2020 would store power that is currently wasted; it has not been built. A 50 MW battery was refused planning here in 2024; while discharging it could have supplied about 175,000 homes.

Ranks 10 of 650 for clean power approved and not built; 15 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Cruachan Hydro ExpansionDrax Power Limited / Stantec UK Pumped Storage Hydroelectricity 600 MW Cannot connect to the grid until 2030, 7 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission · earliest connection 2030 · planning ref ECU00004492
Cnoc Buidhe WindfarmBelltown Power Limited Onshore wind 191 MW167,000 homes Waiting 16 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004767
Sheirdrim Renewable Energy Development - WindScottishPower Renewables Onshore wind 114 MW100,000 homes Refused by the Scottish Government (it decides big energy projects) in 2023Who can move it: the planning appeal inspector · planning ref ECU00001957
Cnoc Buidhe WindfarmBelltown Power Limited Battery 109 MW Waiting 16 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004767
Loch Awe - Eredine Wind FarmRWE Renewables UK Limited Onshore wind 100 MW87,000 homes Waiting 20 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004517
Sloy Hydroelectric Power Station - Pumped Hydro ConversionScottish & Southern Energy Renewables Pumped Storage Hydroelectricity 100 MW Waiting 18 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006088
Corr Chnoc Wind FarmGalileo Green Energy Scotland Limited Onshore wind 86 MW76,000 homes Waiting 17 months for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00006023
Rowan Wind FarmEnergiekontor UK Limited Onshore wind 86 MW75,000 homes Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003230
An Carr Dubh Wind FarmStatkraft UK Limited Onshore wind 86 MW75,000 homes Waiting 3.4 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00004781
Blarghour Wind FarmCoriolis Energy / ESB Onshore wind 84 MW73,000 homes Cannot connect to the grid until 2029, 8 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref EC00005267
Tangy 4 Wind FarmScottish & Southern (SSE) Onshore wind 80 MW70,000 homes Approved 7 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00000673
Earraghail Renewable Energy DevelopmentScottishPower Renewables Onshore wind 78 MW68,000 homes Waiting 4.4 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects) · planning ref ECU00003421

Plus 35 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Argyll, Bute and South Lochaber 384 MW460 MW£1.7m
West Dunbartonshire 0.5 MW0 MWnot visible
Stirling and Strathallan 52 MW193 MWnot visible
Angus and Perthshire Glens 143 MW345 MW£3.4m
Inverness, Skye and West Ross-shire 453 MW1,272 MW£41m

Inverness, Skye and West Ross-shire next door has 453 MW waiting, more than Argyll, Bute and South Lochaber's 384 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.