CONSTITUENCY BRIEFING · ENERGYMAP.APP

Arbroath and Broughty Ferry

MP: Lara Bird (Scottish National Party) Scotland Data to July 2026

Arbroath and Broughty Ferry has 96 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 35,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,808 homes. A 50 MW battery was refused planning here in 2025; while discharging it could have supplied about 175,000 homes.

Ranks 70 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Tealing Solar Energy Park - Phase 2Sirius EcoDev Limited Solar 110 MW40,000 homes Cannot connect to the grid until 2027, 2 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2027 · planning ref ECU00004882
Tealing Battery Energy Storage FarmSirius EcoDev Limited Battery 80 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref ECU00003354
Bankhead, Arbirlot - Battery Energy StorageEcocel Energy Storage Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00178/FULM
Pitkerro Road - Battery Energy StorageVital Energi Utilities Limited Battery 50 MW Refused by Dundee City Council in 2025Who can move it: Dundee City Council · planning ref 24/00813/FULM
Bonnyknox Solar FarmRenewable Energy Systems (RES) Solar 50 MW18,000 homes Waiting 13 months for a planning decisionWho can move it: Angus Council · planning ref 25/00339/FULM
Bindwells Battery Storage FacilityOPDE UK Limted Battery 50 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 25/00249/FULM
Montreathmont Moor Forest - Solar Farm & Battery StorageRenewable Connections Developments Limited Solar 42 MW15,000 homes Cannot connect to the grid until 2029, 7 years after it was approvedWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2029 · planning ref 22/00460/FULM
Hillend Of Lownie - Forfar Solar farmIndustria Resources Llp Solar 30 MW11,000 homes Refused by Angus Council in 2024Who can move it: Angus Council · planning ref 23/00393/FULM
Wellbank - Solar FarmGreentech Solar 25 MW9,100 homes Its grid connection date of 2024 has passed and it is still not generatingWho can move it: the grid operator (NESO) and SSEN Transmission · earliest connection 2024 · planning ref 23/00424/FULM
Denfield FarmSeahills Properties Limited Battery 20 MW Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00285/FULL
Parkhill Farm, Letham Grange - Solar FarmAlphaReal Solar 18 MW6,500 homes Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 23/00272/FULL
Denfield - Solar FarmPeter J Stirling Limited Solar 12 MW4,500 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref 24/00589/FULL

Plus 3 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Arbroath and Broughty Ferry 96 MW30 MWnot visible
Dundee Central 52 MW0 MWnot visible
Angus and Perthshire Glens 143 MW345 MW£3.4m

Angus and Perthshire Glens next door has 143 MW waiting, more than Arbroath and Broughty Ferry's 96 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.