 "pcon24cd": "W07000103",
 "name": "Neath and Swansea East",
 "nation": "Wales",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 28.5,
   "sites": 2
  }
 },
 "number2": {
  "stuck_mw": 27.3,
  "stuck_mw_int": 27,
  "stuck_sites": 6,
  "homes_equivalent": 19000,
  "homes_vs_seat_households": 0.44,
  "stuck_mw_12m_cut": 48.6,
  "consented_not_built_mw_any_age": 49.3,
  "operational_mw": 57.8,
  "operational_homes_equivalent": 36000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 8.3,
  "rank": 177,
  "tech_mix": {
   "onshore wind": 18.0,
   "solar": 9.3
  },
  "tech_summary": "mostly onshore wind",
  "waiting_vs_running": 0.5,
  "projects": [
   {
    "site_name": "Craig Y Perchych, Glais - Solar farm",
    "address": "Craig Y Perchych Glais, Swansea",
    "repd_ref_id": 9777,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 20.0,
    "homes_equivalent": 7300,
    "consented": "2024-12-16",
    "months_waiting": 19.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Melin Court",
    "address": "Land to the East of Merlin Court, Resolven",
    "repd_ref_id": 4893,
    "technology": "Wind Onshore",
    "capacity_mw": 18.0,
    "homes_equivalent": 16000,
    "consented": "2018-05-16",
    "months_waiting": 98.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Carn Nicholas Farm",
    "address": "Land At Carn Nicholas Farm, Bonymaen, Swansea",
    "repd_ref_id": 5593,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 5.0,
    "homes_equivalent": 1800,
    "consented": "2015-12-14",
    "months_waiting": 127.6,
    "status": "Under Construction"
   },
   {
    "site_name": "Tir John Solar Farm",
    "address": "Tir John Landfill St Thomas Swansea",
    "repd_ref_id": 10018,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 3.0,
    "homes_equivalent": 1100,
    "consented": "2023-06-13",
    "months_waiting": 37.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sun Fields, Gelli Bwch Farm -Solar Array",
    "address": "Sun Fields Dream Fields Lane From B4290 To Gelli Bwch Farm Jersey Marine",
    "repd_ref_id": 12911,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.3,
    "homes_equivalent": 500,
    "consented": "2025-04-22",
    "months_waiting": 15.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Brunel Way, Pentrechwyth - Solar Panels",
    "address": "Morrisons Brunel Way Pentrechwyth Swansea",
    "repd_ref_id": 10630,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.7,
    "homes_equivalent": 300,
    "consented": "2022-03-31",
    "months_waiting": 52.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Tesco Extra, Nantyffin Road - Solar Panels",
    "address": "Tesco Extra Nantyffin Road Swansea Enterprise Park",
    "repd_ref_id": 20913,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.7,
    "homes_equivalent": 200,
    "consented": "2026-05-22",
    "months_waiting": 2.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Eurofoods Building",
    "address": "Blakemore Wholesale, Clarion Close, Swansea Enterprise Park, Swansea, West Glamorgan",
    "repd_ref_id": 7262,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2019-04-09",
    "months_waiting": 87.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ffordd Amazon, Crymlyn Burrows Solar Pannels",
    "address": "Amazon - Cwl1 Ffordd Amazon Crymlyn Burrows",
    "repd_ref_id": 8454,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2021-03-10",
    "months_waiting": 64.8,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43355,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 20.7,
  "approved_24m_mw": 20.5,
  "refused_mw": 0.2,
  "submitted_mw": 0.4,
  "sites": [
   {
    "site_name": "John Green Frog Power Compound, John North Road - Battery System",
    "capacity_mw": 20.0,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "Swansea University, Fabian Way - Battery Energy Storage",
    "capacity_mw": 0.5,
    "status": "approved",
    "year": 2022,
    "homes_while_discharging": 1900
   },
   {
    "site_name": "Swansea Enterprise Park, Clarion Close - Energy Storage Facility",
    "capacity_mw": 0.2,
    "status": "refused",
    "year": 2025,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Kemys Way - Micro Energy Storage Facility",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Kemys Way, Swansea Enterprise Park - Battery Energy Storage",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Ferryboat Close, Swansea Enterprise Park - Micro Energy Storage Unit",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Pencaerlan Solar Farm",
   "repd_ref_id": 9984,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 25.0,
   "homes_equivalent": 9100,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3272424",
   "operator": "Greentech Projects Holding UK Limited",
   "address": "Land to the South west of Seven Sisters",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 15 months for a planning decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-04-30",
     "months_waiting": 15
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "John Green Frog Power Compound, John North Road - Battery System",
   "repd_ref_id": 12455,
   "technology": "Battery",
   "capacity_mw": 20.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-01-20",
   "refused": null,
   "planning_authority": "Swansea",
   "planning_ref": "2022/2356/FUL",
   "operator": "Green Frog Power Limited",
   "address": "Tir John Green Frog Power Compound Tir, John North Road, Port Tennant",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-01-20",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Craig Y Perchych, Glais - Solar farm",
   "repd_ref_id": 9777,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 20.0,
   "homes_equivalent": 7300,
   "status": "Awaiting Construction",
   "consented": "2024-12-16",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3279676",
   "operator": "Windel Energy",
   "address": "Craig Y Perchych Glais, Swansea",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-12-16",
     "years_since_consent": 1.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Melin Court",
   "repd_ref_id": 4893,
   "technology": "Wind Onshore",
   "capacity_mw": 18.0,
   "homes_equivalent": 16000,
   "status": "Awaiting Construction",
   "consented": "2018-05-16",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2014/0883",
   "operator": "Muirhall Energy (formerly Infinis)",
   "address": "Land to the East of Merlin Court, Resolven",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 8 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2018-05-16",
     "years_since_consent": 8.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Carn Nicholas Farm",
   "repd_ref_id": 5593,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 5.0,
   "homes_equivalent": 1800,
   "status": "Under Construction",
   "consented": "2015-12-14",
   "refused": null,
   "planning_authority": "Swansea",
   "planning_ref": "2015/1546",
   "operator": "Suncredit UK",
   "address": "Land At Carn Nicholas Farm, Bonymaen, Swansea",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Tir John Solar Farm",
   "repd_ref_id": 10018,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 3.0,
   "homes_equivalent": 1100,
   "status": "Awaiting Construction",
   "consented": "2023-06-13",
   "refused": null,
   "planning_authority": "Swansea",
   "planning_ref": "2022/1907/FUL",
   "operator": "Swansea City and County Council",
   "address": "Tir John Landfill St Thomas Swansea",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-06-13",
     "years_since_consent": 3.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Sun Fields, Gelli Bwch Farm -Solar Array",
   "repd_ref_id": 12911,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.3,
   "homes_equivalent": 500,
   "status": "Awaiting Construction",
   "consented": "2025-04-22",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2023/0356",
   "operator": "Hale Construction Limited",
   "address": "Sun Fields Dream Fields Lane From B4290 To Gelli Bwch Farm Jersey Marine",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-04-22",
     "years_since_consent": 1.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "W07000081",
  "W07000108",
  "W07000097",
  "W07000107",
  "W07000099",
  "W07000085"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}