 "pcon24cd": "E14001274",
 "name": "Hastings and Rye",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 1.2,
  "stuck_mw_int": 1,
  "stuck_sites": 3,
  "homes_equivalent": 400,
  "homes_vs_seat_households": 0.01,
  "stuck_mw_12m_cut": 1.2,
  "consented_not_built_mw_any_age": 1.2,
  "operational_mw": 0.0,
  "operational_homes_equivalent": 0,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.8,
  "rank": 400,
  "tech_mix": {
   "solar": 1.2
  },
  "tech_summary": "all solar",
  "waiting_vs_running": null,
  "projects": [
   {
    "site_name": "Camber Sands Holiday Park, Lydd Road - Solar Panels",
    "address": "Camber Sands Holiday Park, Lydd Road, Camber",
    "repd_ref_id": 16400,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2024-07-08",
    "months_waiting": 24.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Combe Haven Holiday Park, Harley Shute Road - Solar Panels",
    "address": "Combe Haven Holiday Park, Harley Shute Road, St Leonards-on-sea",
    "repd_ref_id": 13499,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2023-03-06",
    "months_waiting": 40.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Morrisons, Queens Road - Solar Panels",
    "address": "Morrisons, 170 Queens Road",
    "repd_ref_id": 12196,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-11-16",
    "months_waiting": 44.5,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 46904,
  "seat_total_gbp": 4300000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 0.2,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Castleham Road - Energy Storage System",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001088",
  "E14001239",
  "E14001570"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}