 "pcon24cd": "E14001248",
 "name": "Gloucester",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 7.2,
  "stuck_mw_int": 7,
  "stuck_sites": 10,
  "homes_equivalent": 2600,
  "homes_vs_seat_households": 0.05,
  "stuck_mw_12m_cut": 7.8,
  "consented_not_built_mw_any_age": 8.5,
  "operational_mw": 0.0,
  "operational_homes_equivalent": 0,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 8.8,
  "median_months_to_decision": 1.8,
  "rank": 242,
  "tech_mix": {
   "solar": 7.2
  },
  "tech_summary": "all solar",
  "waiting_vs_running": null,
  "projects": [
   {
    "site_name": "Unilever UK, Corinium Avenue - Solar Panels",
    "address": "Unilever UK Corinium Avenue",
    "repd_ref_id": 16178,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 3.5,
    "homes_equivalent": 1300,
    "consented": "2024-05-22",
    "months_waiting": 26.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Hempsted Lane - Solar Array",
    "address": "Hempsted Waste Management Site, Gloucester",
    "repd_ref_id": 11156,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 2.0,
    "homes_equivalent": 700,
    "consented": "2023-08-18",
    "months_waiting": 35.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gloucestershire College - Photovoltaic Solar Panels",
    "address": "Gloucestershire College, Llanthony Road, Gloucester",
    "repd_ref_id": 9875,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2022-05-04",
    "months_waiting": 51.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sainsburys Supermarket -  Solar Panels",
    "address": "Sainsburys Supermarket, Barnett Way, Barnwood, Gloucester",
    "repd_ref_id": 19984,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2026-01-05",
    "months_waiting": 6.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Arlingham House, Quedgeley -  Solar Panels",
    "address": "Arlingham House, Falcon Close, Quedgeley, Gloucester",
    "repd_ref_id": 9769,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2021-11-03",
    "months_waiting": 57.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Bruton Way -  Solar PV Panels",
    "address": "Gl1 Bruton Way, Gloucester",
    "repd_ref_id": 17381,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-12-05",
    "months_waiting": 19.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Tenpin Centre, Severn Barnwood Link Road - Solar Panels",
    "address": "Tenpin Centre Severn Barnwood Link Road",
    "repd_ref_id": 14838,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-10-25",
    "months_waiting": 33.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gloucester Academy",
    "address": "Painswick Road, Gloucester, Gloucestershire",
    "repd_ref_id": 8102,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2021-05-17",
    "months_waiting": 62.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Unilever UK - Solar Panels",
    "address": "Unilever UK, Corinium Avenue, Gloucester",
    "repd_ref_id": 18310,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-04-03",
    "months_waiting": 16.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Alpha Colour Printers, Waterwells Drive - Solar Panels",
    "address": "Alpha Colour Printers Waterwells Drive Quedgeley",
    "repd_ref_id": 20657,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2026-05-06",
    "months_waiting": 2.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Francis And Lewis International, Waterwells Drive - Solar Panels",
    "address": "Francis And Lewis International Waterwells Drive",
    "repd_ref_id": 12240,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-11-07",
    "months_waiting": 44.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Shirt Factory - Solar Panels",
    "address": "The Shirt Factory, 51 Derby Road, Gloucester",
    "repd_ref_id": 18584,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-06-09",
    "months_waiting": 13.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gloucester Royal Hospital - Solar Panels",
    "address": "Gloucester Royal Hospital, Great Western Road, Gloucester",
    "repd_ref_id": 9178,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2021-07-05",
    "months_waiting": 60.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Quayside House - Solar Panels",
    "address": "Site Of The Former Quayside House Quay Street Gloucester Gloucestershire",
    "repd_ref_id": 8864,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2021-05-11",
    "months_waiting": 62.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Morrisons Supermarket, Glevum Way - Solar Panels",
    "address": "Morrisons Supermarket, Glevum Way, Gloucester",
    "repd_ref_id": 14591,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2023-10-03",
    "months_waiting": 34.0,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 48790,
  "seat_total_gbp": 4500000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 50.0,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Sudmeadow Road, Hempsted - Battery Energy Storage System",
    "capacity_mw": 50.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 175000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Sudmeadow Road, Hempsted - Battery Energy Storage System",
   "repd_ref_id": 17343,
   "technology": "Battery",
   "capacity_mw": 50.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-11-21",
   "refused": null,
   "planning_authority": "Gloucester",
   "planning_ref": "24/00732/FUL",
   "operator": "Greenfield Energy Developments Limited",
   "address": "N/O Sudmeadow Road, Hempsted, Gloucester",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-11-21",
     "years_since_consent": 0.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Unilever UK, Corinium Avenue - Solar Panels",
   "repd_ref_id": 16178,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 3.5,
   "homes_equivalent": 1300,
   "status": "Awaiting Construction",
   "consented": "2024-05-22",
   "refused": null,
   "planning_authority": "Gloucester",
   "planning_ref": "24/00190/PRIOR",
   "operator": "Unilever UK",
   "address": "Unilever UK Corinium Avenue",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-05-22",
     "years_since_consent": 2.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Hempsted Lane - Solar Array",
   "repd_ref_id": 11156,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 2.0,
   "homes_equivalent": 700,
   "status": "Awaiting Construction",
   "consented": "2023-08-18",
   "refused": null,
   "planning_authority": "Gloucester",
   "planning_ref": "22/00365/FUL",
   "operator": "Enovert South Limited",
   "address": "Hempsted Waste Management Site, Gloucester",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-08-18",
     "years_since_consent": 3.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001386",
  "E14001542",
  "E14001240"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}